Picture: North West MEC for Health, Sello Lehari
By KEDIBONE MOLAETSI
29 September 2026 – The North West Department of Health has clarified the circumstances surrounding the R28 million payment to MIB Infrastructure Development for professional services related to the planned upgrading and modernisation of General De La Rey Hospital in Lichtenburg. The department said the payment related to professional services rendered during the project’s planning and design stages, following a revised infrastructure plan that retained the existing hospital, instead of replacing it with a new facility.
North West MEC for Health, Sello Lehari said the appointments of Bagale Consulting and MIB Infrastructure Development were linked to different hospital development plans. Lehari said these were not simply two appointments for exactly the same project.
“Bagale’s appointment related to the proposed new Lichtenburg Hospital, while MIB’s appointment related to the subsequent decision to retain and upgrade the existing General De La Rey Hospital.
“The process dates back to 2008, when the Department of Public Works appointed Bagale Consulting to plan, design and oversee the construction of a proposed new Lichtenburg Hospital. The original plan was to replace General De La Rey Hospital and Thusong Hospital with a single district hospital,” he said.
Lehari further said, however, following the closure of Thusong Hospital, communities in Itsoseng and Sheila raised concerns about access to the proposed facility, which would have been approximately 40 km away. He added that the department subsequently revised its infrastructure plan to include upgrading Itsoseng Community Health Centre into a district hospital and retaining and modernising General De La Rey Hospital.
“MIB Infrastructure Development was then appointed to provide professional services for the existing hospital’s upgrade. The department acknowledged that approximately R28 million was paid to MIB for professional services associated with the planned hospital upgrade.
“The initial project brief was to upgrade the facility to approximately 120 beds, including support and auxiliary services. The professional team progressed with planning and design up to Stage 3,” said Lehari.
He said following engagements with the National Department of Health, the proposed capacity was reduced from approximately 120 beds to 81 beds. Lehari said the change required the professional team to revise the concept design and return to Stage 2 before realigning the Stage 3 documentation.
“No additional invoice was submitted for the redesign and rework resulting from the revised project brief. The approximately R28 million should not be characterised as payment merely for inception and concept-viability services.
“It relates to professional services rendered during the course of the project under the original and subsequently revised project requirements. We would continue reconciling payments against the contract, deliverables, certifications and work performed, adding that recovery measures would be pursued if improper or excessive payments were established,” he said.
Lehari said the dispute over the appointments was taken to the High Court, which declared MIB’s appointment unlawful and set it aside, while confirming the validity and enforceability of Bagale Consulting’s appointment for the proposed new Lichtenburg Hospital. He said the court also found that architect Tafadzwa Mtisi’s professional registration certificate had expired by the tender closing date, making the bid technically non-responsive in that respect.
“This finding must be distinguished from the separate allegation that Mtisi’s credentials were used without his knowledge or consent, which still requires verification. The department would not prejudge allegations, but would investigate credible evidence and take appropriate action where wrongdoing was established.
Hospital project to proceed.
“Following the termination of MIB’s appointment and the court ruling, it was engaging Bagale Consulting on taking forward the General De La Rey Hospital upgrade from the stage at which MIB’s involvement ended,” said Lehari.
He said the process would be conducted within the applicable legal, contractual and procurement framework. Lehari said they would explore preserving and adapting professional designs developed for the proposed new Lichtenburg Hospital for future hospital developments, subject to the necessary approvals.
“The department remained committed to ensuring that public resources were protected and that communities in Lichtenburg, Itsoseng, Sheila and surrounding areas ultimately received accessible and sustainable hospital infrastructure,” he said.